With only one month’s notice, Agility needed to prepare our open yard storage in North Rumaila for 15,000 CBMs of coated pipes. The preparation process to receive and store the pipes required us to conduct ground compaction and construct concrete sleepers to meet client specifications. Agility coordinated with a third-party Iraqi transport company to receive 25 trucks per day from Umm Qasr Port to North Rumaila and conduct the offloading operation using two cranes to ensure that everyone was operating in an incident-free, safe working environment. We managed to complete the pipe operation within 22 days without any delays to the customer.